Earned value management in plain terms: what EVM tells you and what it needs

On this page

Short answer: earned value compares three numbers: what you planned to have done by now, what you have actually done, and what it cost. From those you get two ratios that tell you whether the project is ahead or behind on schedule and over or under on cost. It works only when you have a baseline and honest progress.

The three numbers

The two ratios

Example: budget 100,000, planned 40% done, actually 30% done, spent 45,000. PV is 40,000, EV is 30,000, AC is 45,000. SPI is 0.75 and CPI is about 0.67. You are behind and over budget, and the numbers show it before a status meeting does.

What you need first

  1. A baseline. A saved plan with dates and budget to compare against.
  2. A budget per piece of work. Without it, PV has nothing to measure.
  3. Honest progress. Percent complete should come from finished work, not from a hopeful guess.
  4. Actual cost. Time and expenses recorded as they happen.

If you do not have these, start with health, overdue work and milestones. EVM on weak data gives false confidence.

What a tool can do

In NUSK, baselines let you compare slipped dates on the Gantt chart and in the baseline variance report. Timesheets, rate cards and expenses record actual cost, and project and portfolio overviews roll up completion, overdue work, risks, budget and earned value. The Health Score adds schedule slip and cost to the picture, with reasons.

Mistakes

When NUSK is not the right choice

If you need formal EVM reporting to a contract standard, confirm that the format you must submit is supported before you commit.