On this page
Short answer: earned value compares three numbers: what you planned to have done by now, what you have actually done, and what it cost. From those you get two ratios that tell you whether the project is ahead or behind on schedule and over or under on cost. It works only when you have a baseline and honest progress.
The three numbers
- Planned value (PV): the budgeted cost of the work that should be finished by today.
- Earned value (EV): the budgeted cost of the work actually finished.
- Actual cost (AC): what you have spent.
The two ratios
- Schedule performance index (SPI) = EV / PV. Below 1 means behind schedule.
- Cost performance index (CPI) = EV / AC. Below 1 means over budget.
Example: budget 100,000, planned 40% done, actually 30% done, spent 45,000. PV is 40,000, EV is 30,000, AC is 45,000. SPI is 0.75 and CPI is about 0.67. You are behind and over budget, and the numbers show it before a status meeting does.
What you need first
- A baseline. A saved plan with dates and budget to compare against.
- A budget per piece of work. Without it, PV has nothing to measure.
- Honest progress. Percent complete should come from finished work, not from a hopeful guess.
- Actual cost. Time and expenses recorded as they happen.
If you do not have these, start with health, overdue work and milestones. EVM on weak data gives false confidence.
What a tool can do
In NUSK, baselines let you compare slipped dates on the Gantt chart and in the baseline variance report. Timesheets, rate cards and expenses record actual cost, and project and portfolio overviews roll up completion, overdue work, risks, budget and earned value. The Health Score adds schedule slip and cost to the picture, with reasons.
Mistakes
- Using EVM on a project with no baseline.
- Counting a task as 90% done for weeks.
- Comparing projects that measure progress differently.
- Reading one month's number as a trend.
When NUSK is not the right choice
If you need formal EVM reporting to a contract standard, confirm that the format you must submit is supported before you commit.